by dede.derosa | Nov 6, 2020 | WPCA, WPCA Update
Costs have escalated substantially since 2012 and are currently estimated at $39,568 plus the cost of lateral connection with no apparent ceiling. There is a perception that the WPCA has not established a budget and is not focused on cost containment In 2012 OLSBA...
by Matt | Sep 18, 2020 | WPCA Update
2020 Sep 8_OLSBA Overall PROJECT COST Breakdown
by Matt | Sep 18, 2020 | WPCA Update
WPCA Report Old Lyme Shore Beach Association Fall Meeting September 12, 2020 Pump Station / Shared Infrastructure Town of Old Lyme reviewed an easement for sewer pipes to go through Sound View streets and Gorton Ave (Odor Control Station) at the September 8 BOS public...
by Matt | Jun 20, 2020 | WPCA Update
2020 June 20 OLS TIMETABLE SCHEDULE 0620_OLSBA Schedule Milestones-001 PROJECT MILESTONES OLD LYME SHORES BEACH ASSOCIATION SEWERS AND OTHER INFRASTRUCTURE PROJECT 20101210.B10 06/20/2020 I) Schedule Milestones A) Connecticut Environmental Protection Act Review...
by Matt | Jun 20, 2020 | WPCA Update
2020 June 20 SHARED INFRASTRUCTURE TIMETABLE SCHEDULE Milestones (1) PROJECT MILESTONES OLD LYME SHARED INFRASTRUCTURE PROJECT 20101210.B40 6/20/2020 I) Schedule Milestones A) Connecticut Environmental Protection Act Review Completed – October 2, 2017 B)...
by Matt | Jun 20, 2020 | WPCA Meeting Minutes, WPCA Update
2020 June 20 WPCA SPRING MEETING report (1) WPCA Report OLS Spring Virtual Meeting June 20, 2020 Pump Station / Shared Infrastructure –Agreement reached with Town to add Sound View into the Cost Sharing agreement – reduces our share from 30% to 21%...