2020 June 20 WPCA SPRING MEETING report (1)

 

WPCA Report
OLS Spring Virtual Meeting
June 20, 2020

Pump Station / Shared Infrastructure
–Agreement reached with Town to add Sound View into the Cost Sharing agreement – reduces our
share from 30% to 21%
–Finalizing easements with Town and private properties for pump station, sewer pipes and odor control
(OLS Ballfield)
–Working on additional permits with AMTRAK, DOT, DEEP (Coastal Resources & Flood Management
–Completed design review and construction bids scheduled to be reviewed in Dec –
–CWF Construction Grant / Loan review by DEEP – takes about 4 months
Estimated Construction start date April 2021
Estimated completion date August 2022
– June 20, 2020 Timetable Project Milestones posted on website
– June 20 Pump Station Odor control system PowerPoint posted on website
Old Lyme Shores Infrastructure Project
Estimated costs updated by F&O on May 6 to be $39,000 per EDU or $2561 per year over 20 years
— all residents to share equally in the infrastructure costs and Operation & Maintenance and flow
expenses
–homeowners are required to connect to the new sewer system and abandon their septic system
– Dec 2019 PowerPoint on Sewer Hook Up and Septic System abandonment posted on
website
–includes estimates for Clean Water Fund eligible grant and OLS secured loans for ineligible expenses
– Ineligible expenses include Buy in fees to East Lyme & New London; Storm Drainage
improvements
– May 6, 2020 Estimated Costs by Fuss & O’Neill posted on website
–need some minor road easements from some residents – Bryan Even & Matt Merritt will be reviewing
–road widths, road safety improvements and a new ramp at end of Billow Rd will be reviewed at Fall
meeting
Estimated Construction start date Jan 2021
Estimated completion date August 2022
– June 20, 2020 Timetable Project Milestones posted on website
Stormwater Management / Drainage
Design is virtually complete – goal is to control the flow of rainwater to minimize flooding
— control the flow of rain water through the addition of some curbing to funnel water to catch basins to
a new collector pipe along Bellaire Road and discharging into Long Island Sound
–catch basins located to catch flow from existing swales/drains in backyards (we are not going on
private property)
–provide new connections to sump pumps currently draining into catch basins
–larger outfall in crabbing rocks jetty from 12” to 24”
–secondary outfall into Sheffield Brook below the culverts

Because of the large scope of the project, DEEP Coastal Resources requires a major review and coastal
area management permit (Structural Draining & Fill) which normally has a 4-6-month review
CWC
Tentative schedule for next 2 months – all work below Rte. 156
-Brightwater
-Seal Lane to Billow and Billow – to July 17
-Sea lane Saltaire and Saltaire -to Aug 14
-Seal lane to Seaspray
CWC/VMS focused on completing their work with existing customers through Oct.
Additional work for residents will be entertained by VMS in Nov.
–deep service meter
–deep service connection to house
If residents want work done before Nov, another contractor can be utilized once the new deep main has
been activated and resident must complete application to CWC to coordinate tapping the main line
Wells
OLS has 76 wells most of which encroach on the 75’ separation from the sewer line required in the DPH
Health Code
-OLS will be installing heavy duty sewer pipe to meet the 75’ separation requirement
33 wells are within the 25’ separation from the sewer line
– It is anticipated that the homeowners with wells within 25 feet of sewer and lateral piping will have to
abandon their wells.
– we anticipate receiving the official notification from DPH soon!
– We have applied for and anticipate receiving a grant from DPH in Sept to assist well owners in
connecting to CWC and abandoning their wells. (25% subsidy and a 75% loan paid over time)
– DPH requires that we wait until after CWC has completed their work and OLS bids in accordance with
CT State bidding requirements.
-Each well owner that participates in the grant will assume their costs of connection and abandonment
-Goal is to have as many well owners connect to CWC to minimize tearing up our new road in the future.
– May 8, 2020F&O Water source study (wells separation from sewers) listing all wells

Other WPCA postings on website include:
WPCA Updates – Dec 20, 2019 & April 11, 2020
WPCA Meeting Minutes – 2019 August 17, Nov 23 , & Dec 14
– 2020 May 25