This post provides links to all current bid-related documents for the Shared Infrastructure which includes the pump house, odor control station, and forced main line from Sound View to East Lyme.

Bid Process Timeline:

April 13:  DEEP approval to advertise

April 19:  Bid Advertisement is posted

May   1:  Pre-bid meeting

May 19:  Commence bid opening/bid evaluation (F&O)

Bid Documents and Addenda

Old Lyme Shared Infrastructure_Project Manual Volume 1 of 2

Old Lyme Shared Infrastructure_Project Manual Volume 2 of 2

Old Lyme Shared Infrastructure_Project_Contract Drawings Stamped

Shared Infrastructure_Addendum 1 of 4

Shared Infrastructure_Addendum 2 of 4

Shared Infrastructure_Addendum 3 of 4

Shared Infrastructure_Addendum 4 of 4

 

List of Bidders

Bid Summary & Tabulation_Draft