2020 June 20 OLS TIMETABLE SCHEDULE 0620_OLSBA Schedule Milestones-001
PROJECT MILESTONES
OLD LYME SHORES BEACH ASSOCIATION SEWERS AND OTHER
INFRASTRUCTURE PROJECT
20101210.B10
06/20/2020
I) Schedule Milestones
A) Connecticut Environmental Protection Act Review Completed – October 2, 2017
B) Unified Three Association Consent Order Issued by DEEP – February 14, 2018
C) Finalized New London IMA – April 27, 2018
D) Finalized East Lyme IMA – July 24, 2018
E) A/E Agreement Amendment #1 Signed – September 16, 2018
F) Clean Water Fund Grant/Loan Application Submittal – October 3, 2018
G) Clean Water Fund Grant/Loan Approval – April 4, 2019
H) Water System Design Authorized – September 20, 2019
I) Water System Kick Off Meeting – September 30, 2019
J) Water System Begin Detailed Design – October 1, 2019
K) Wastewater Preliminary Design Submittal – January 3, 2020
L) Water Final Design Submittal – November 1, 2019
M) Connecticut Water Review Period Ends – November 8, 2019
N) Water Final Bid Documents February 18, 2020
O) Water Advertisement to Bid – February 20, 2020
P) Water Contract Authorized February 27, 2020
Q) Water Mainline and Construction within ROW Begins – March 2020
R) Wastewater Detailed Design Draft Submittal* – July 15, 2020
S) Detailed Design Complete* – July 30, 2020
T) Advertisement to Bid* – August 15, 2020
U) Construction Bids Due* – September 15, 2020
V) Recommendation to Award to Association* – September 15, 2020
W) Recommendation to Award to DEEP* – September 16, 2020
X) Submit CWF Construction Application* – September 24, 2020
Y) Award Construction Contract* – December 30, 2020
Z) Begin Construction* – January 15, 2021
AA) Mainline Water and construction Completed – October 1, 2020
F:\P2010\1210\B10_OLSBA Design\Schedule\20200620_OLSBA Schedule Milestones.Docx
Corres.
BB) Begin Water Service Construction – October 4, 2020
CC) Water Service Construction Completed – February 12, 2021
DD) Sewers/Roadways Construction Substantially Complete** – Jan 27, 2022
EE) Project Closeout/Final Roadway Paving – May 19, 2022
FF) Begin Connecting Properties to Infrastructure** – June 30, 2022
*Predicated upon DEEP/DPH approval of technical designs for well encroachment, Coastal
Resources Permit and award of Flood Management Certificate and Easement negotiations for
roadways by August15, 2020.
**Predicated upon no Summer or Winter construction shutdown